Compressor updgrades
We are supporting National Gas in replacing and upgrading its compressors on the NTS to ensure the pipeline network and assets continue to deliver the capabilities required across the country.
In 2023, we were awarded the enabling works, pipeline diversions and mechanical and civil packages associated with the new 60in Compressor install at Hatton Compressor Station, replacing two existing Units that no longer complied with the Industrial Emissions Directive. Over the two-and-a-half-year build, we were responsible for the new Station expansion, including installing the new Compressor and associated equipment, as well as the portal frame CAB building.
In 2025, we were awarded a contract to install a new 15MW Compressor at the Wormington Compressor Station. The project forms part of the Medium Plant Combustion Directive (MCPD), which aims to deliver increased sustainability and reduce air pollution.